Wednesday, October 19, 2016

Tuesday, September 27, 2016

Kitchen

Kitchen nearing completion.  Still waiting on glass splashback.

Pantry Shelving (looking left).
Pantry Shelving (looking straight in).

Saturday, September 24, 2016

Tuesday, August 16, 2016

Wednesday, June 15, 2016

Frame Up

Frame almost complete. Builder said should be done including the Windows by the end of the day.

Tuesday, June 14, 2016

Friday, June 10, 2016

Build Watch

Build Watch camera active on site.  Images on their website update every 15mins, so i won't have to run out their everyday to see if anything has happened.

Wednesday, June 8, 2016

Pipes and Power



Stormwater and sewer pipes installed. Also power has been connected, along with a security camera.

Saturday, May 7, 2016