Maxwell House MkII - Eden Brae Foxley 30
Links
Build Watch Camera
Wednesday, October 19, 2016
Nearly Done
Kids bathroom shower
Kids bathroom basins
Master Ensuite
Friday, October 7, 2016
Driveway Poured
Thursday, October 6, 2016
Landscape Plan
Friday, September 30, 2016
Driveway Formed Up
Tuesday, September 27, 2016
Kitchen
Kitchen nearing completion. Still waiting on glass splashback.
Pantry Shelving (looking left).
Pantry Shelving (looking straight in).
Saturday, September 24, 2016
Outdoor Painting Complete
Handrail still to be fitted to the Alfresco and steps.
Thursday, August 25, 2016
Garage Door Fitted
Wednesday, August 17, 2016
Gyprock Done
Tuesday, August 16, 2016
Gyprock almost complete
Builder had to come back and fix the open wall for the Living Room.
Monday, August 15, 2016
Insulation Done and Gyprock Delivered
Wednesday, August 10, 2016
Camera Moved Inside
The camera has now been moved inside.
Taking Shape
Sunday, July 31, 2016
Bricks Cleaned
Tuesday, July 26, 2016
Bricks Finished, Roof On
Wednesday, June 22, 2016
Bricks Arrived
Bricks arrived and so did the brick layers.
Wednesday, June 15, 2016
Frame Up
Frame almost complete. Builder said should be done including the Windows by the end of the day.
Tuesday, June 14, 2016
Framing Started
Workers arrived at about 1:15pm today and put up some of the frame.
Friday, June 10, 2016
Build Watch
Build Watch camera active on site. Images on their website update every 15mins, so i won't have to run out their everyday to see if anything has happened.
Thursday, June 9, 2016
Frame Arrived
Frame and windows arrived.
Wednesday, June 8, 2016
Pipes and Power
Stormwater and sewer pipes installed. Also power has been connected, along with a security camera.
Tuesday, May 31, 2016
Slab Done
Slab has finally been poured.
Friday, May 27, 2016
Slab Formed Up
Slab has been formed up.
Saturday, May 7, 2016
Block Leveled
The block has finally been leveled and is ready to start building.